WEEK 1
Work began this week on Highland Av at the corner of Kelsea Av. continued down Highland Av to Forest Hills and down Forest Hills to Towle Street.
Work ended on Friday afternoon and will resume on Monday morning at 7:00 am.
Next week work will be on Highland Av. crossing the school playground along highland Place and over the bank to Armstrong Avenue.
If you have any questions regarding the project or the schedule of work being done, please contact the Walter Johnson at the Town office at 838-6376.
Sorry for any inconvenience you may have experienced this week.
If you can avoid the Highland Av. area for the next two weeks if would be greatly appreciated!
All work in the area of the school will be completed by September 2, opening day of school.
Have a great weekend!
Walter
|