10/14/14

Plow fronts are mounted on all the trucks. Van maintenance continues. Hopper for pick-up at shop for spreader chain installation.

Grade portions of the Plains, Brooks, Perch pd. and Sweeney rds.  Haul gravel to Jackman neighborhood, grade.

Budget preparation for monthly dept. head meeting Wednesday. Prepare for selectmen meeting this afternoon. Topics  to include paving costs and schedule,  meters, Quimby rd, van improvements and anything else.

Meet with contractor on Armstrong Ave in regards to homeowner wastewater line questions/location.